Columbia Pike/Hwy 31 Widening by TDOT

State Route 6, also known as Columbia Pike, Highway 31 and Main Street in Spring Hill, has been identified by the Tennessee Department of Transportation as an area that needs to be addressed due to the continuing population expansion in Middle Tennessee.  TDOT has come up with concept plans for the widening of Hwy 31 to 4 lanes starting in Franklin and extending south through Thompson's Station and into Spring Hill. 

This is a State of Tennessee Department of Transportation project and this page will be updated as information is provided. 


April 10th, 2025

The Tennessee Department of Transportation (TDOT), accepted the Town of Thompson’s Station request, as part of the Statewide Partnership Program (SPP), to accelerate the Highway 31/Columbia Pike Widening Project. By partnering with TDOT, the Town was able to move preliminary engineering work on the Town’s top roadway improvement priority from 2029 to 2026.

Over the past few years, Mayor Stover has made it a priority to work directly with our state elected officials, especially Senator Johnson and Representative Reeves, members of the Greater Nashville Regional Council, and the TDOT leadership, to impress upon them the Town’s willingness to proactively address regional infrastructure issues that impact the quality of life for residents on a daily basis. With TDOT’s announcement on Monday, April 7th, 2025, that investment in time and effort has paid dividends.

The 31 Widening Project has been the Town’s top roadway priority for nearly a decade through successive BOMAs. In 2019 and 2020, the BOMA, Planning Commission, and Town Staff worked collaboratively with TDOT to set the groundwork for this project with review and consideration of the cross-section for the proposed widening of 31. As part of that collaboration, we secured a cross-section that includes a landscaped median in order to better reflect the Town’s character along portions of 31. The BOMA approved the All Aboard Major Throughfare Plan in 2022, which reaffirmed that the Columbia Pike/Highway 31 Widening Project remained as the Town’s top roadway priority. In 2023, TDOT released the initial 10 Year Plan, including the 31 Widening Project, but with preliminary engineering to begin in 2029. Last November, the Town secured a meeting with the TDOT Commissioner to make the Thompson’s Station case for TDOT to accelerate the Columbia Pike Widening Project based on the negative impacts to the Town’s residents and businesses related to the increasing congestion and gridlock along the corridor.

As part of the SPP program, TDOT requires local jurisdictions to provide local funds to help accelerate the project. Late last year, the Thompson’s Station BOMA came to the consensus that $15 million in local funds would be included with the Town’s SPP proposal to partner with TDOT on accelerating this critical roadway project. With the announcement of TDOT’s updated 10 Year, TDOT committed to a strong partnership with Thompson’s Station and brought the Town’s long-standing goal of fixing Columbia Pike one step closer to reality!


You can find local information on TDOT maintained highways at https://www.tn.gov/tdot/find-local-information.html including phone numbers for specific departments (eg. Survey & Design; Right-of-Way & Utilities; Bridge; Traffic; Community Relations; etc.)

TownwideVicinity_Hwy31Widening Opens in new window
Columbia Pike Vicinity Map

The slideshow below is the concept design for Hwy 31 widening prepared by TDOT and includes only the sections within Thompson's Station Town Limits, from Buckner Rd to the Tollgate North Entrance.  

 TDOT Hwy 31 - Concept Plan Slideshow